street improvement mapAs the Sutter Medical Center, Sacramento midtown expansion project nears completion, final street improvements with the City of Sacramento are underway and are scheduled to continue through May 21.  The area of work extends from K Street to Capitol Avenue between 27th and 29th streets. It involves lowering manholes, grinding, repairing, overlaying and paving, sealing and striping.

Depending on the work to be completed, there will be traffic controls in place that include partial to full lane closures, as well as street closures.  The overlaying and paving will occur the second week in the evenings and overnight (6 p.m. to 6 a.m.) due to the possibility of street closures. There is noise from grinding and trucks, as well as smells from paving and sealing associated with this work.

Here is the day-to-day schedule of street activities:

  • 7 a.m.-7 p.m. Saturday, May 2: Grinding throughout all streets. This will include street closures and detours for portions of the day. This will be noisy work, with the grinding of streets and the beeping of trucks backing up.
  • 6 p.m. Monday, May 4, to 6 a.m. Tuesday, May 5: Laying out, digging out and base repairs on many streets. This will include traffic controls and lane closures. There will be some noisy work and includes trucks backing up.
  • 6 p.m. Tuesday, May 5, to 6 a.m. Wednesday, May 6: Base repairs. This will include traffic controls and lane closures, along with some noisy repair work and trucks backing up.
  • 6 p.m.-6 a.m. nightly from Wednesday, May 6, to the morning of Saturday, May 9: Level, overlay and pave. This will include traffic controls and lane closures, along with some noise from trucks as well as smell from the paving.
  • 7 a.m.-4 p.m. daily from Monday, May 11, through Tuesday, May 19: Raising the manhole covers throughout the streets. This will include traffic controls and lane closures, along with noise from trucks.
  • 7 a.m.-4 p.m. both Thursday, May 14, and Friday, May 15: Slurry seal. This will include traffic controls and lane closures, along with noise from trucks and smells.
  • 7 a.m.-4 p.m. both Wednesday, May 20, and Thursday, May 21: Striping of all streets. This will include traffic controls and lane closures.

We understand this is disruptive, and we appreciate your understanding and patience as we complete these street improvements. Please contact Pam Brink at BrinkP@sutterhealth.org you have any questions or need additional information. Check out the map for more details of the work to be completed.

Posted by on May 1, 2015 in News, Sutter District, Traffic & Construction Updates | 0 comments

Leave a Reply

Your email address will not be published. Required fields are marked *