A New Era in Health Care
The Sutter Medical Center, Sacramento Expansion




Wall Removal Creates Challenge for Construction Crews

by Gary Zavoral on January 27, 2012

in Anderson Lucchetti Women's and Children's Center,Buildings,News,Traffic & Construction Updates

One of the most difficult and dangerous tasks in the construction of the Sutter Medical Center, Sacramento expansion project is near completion, reports construction contractor, The Boldt Company.

Construction crews had very little room to work in order to remove the wall panels from Sutter General Hospital.

Sutter General Hospital and the new Anderson Lucchetti Women’s and Children’s Center will be connected by a unique, three-story spanning structure on the second, third and fourth floors. Steel for the spanning structure was erected over L Street in 2011, but it has yet to be connected to Sutter General Hospital. In order to tie into the existing hospital, precast exterior panels forming a large portion of Sutter General’s southern wall had to be removed. 

“On a scale of 1 to 10, it was a 9 out of 10 on danger,” said Brian Baudot, a foreman with Boldt construction partner Austerman. “There was no room for error.”

Austerman was in charge of getting the panels down from the building safely. After numerous meetings between Austerman and Boldt staff, a plan of action was adopted.

The panels, weighing about 15,000 pounds each, needed to be removed in sections. The first panel took four or five days to remove.

“If we would have cut it in the wrong way, the whole thing would have crashed down,” Baudot said.

To ensure safety, Austerman removed the panels selectively in 1,500-pound pieces with a forklift that has a capacity of 2,000 pounds.

Crews worked inside Sutter General Hospital and outside in order to safely remove each panel.

“It required a lot of heavy, heavy coordination between everybody,” said Pete Tinoco, Boldt’s superintendent on the major remodel of Sutter General Hospital. “We had guys inside and outside at the same time, keeping an eye on the panels as they were moving, just to make sure they didn’t hang up on something and create a fall hazard.”

Because of this, communication was vital. Each panel piece required a different process of removal. It was difficult to have any kind of standard process in place.

The largest panel to be removed in one piece weighed more than 8,000 pounds. It was removed from the third floor with chain falls, a boom lift and the tower crane.

Having a very narrow bay to work in added to the challenging task.

“We didn’t have a lot of latitude for moving, or for equipment that we would have rather used,” Baudot said.

Even with all the challenges, all panels from the first, second and third floors were removed safely, on time and on schedule. Boldt and Austerman workers are now awaiting the go-ahead from the California Office of Statewide Health Planning & Development, or OSHPD, to safely remove the panels from the fourth floor of Sutter General. With that accomplished, construction crews can then finish the spanning structure by finishing the spanning structure and connecting the two hospitals. When the expansion project is completed in late 2013, this spanning structure will seamlessly connect all of Sutter Medical Center’s acute-care services under one roof.

{ 1 comment… read it below or add one }

Molly January 19, 2012 at 12:29 pm

It is amazing to see what hard work these men have put into this project and how many lives the work they have completed is going to touch. Not everyone can do what they do, but thank God they do it so well!

Reply

Leave a Comment

Previous post: