A New Era in Health Care
The Sutter Medical Center, Sacramento Expansion




One of the most difficult and dangerous tasks in the construction of the Sutter Medical Center, Sacramento expansion project is near completion, reports construction contractor, The Boldt Company.

Construction crews had very little room to work in order to remove the wall panels from Sutter General Hospital.

Sutter General Hospital and the new Anderson Lucchetti Women’s and Children’s Center will be connected by a unique, three-story spanning structure on the second, third and fourth floors. Steel for the spanning structure was erected over L Street in 2011, but it has yet to be connected to Sutter General Hospital. In order to tie into the existing hospital, precast exterior panels forming a large portion of Sutter General’s southern wall had to be removed. 

“On a scale of 1 to 10, it was a 9 out of 10 on danger,” said Brian Baudot, a foreman with Boldt construction partner Austerman. “There was no room for error.”

Austerman was in charge of getting the panels down from the building safely. After numerous meetings between Austerman and Boldt staff, a plan of action was adopted.

The panels, weighing about 15,000 pounds each, needed to be removed in sections. The first panel took four or five days to remove.

“If we would have cut it in the wrong way, the whole thing would have crashed down,” Baudot said.

To ensure safety, Austerman removed the panels selectively in 1,500-pound pieces with a forklift that has a capacity of 2,000 pounds.

Crews worked inside Sutter General Hospital and outside in order to safely remove each panel.

“It required a lot of heavy, heavy coordination between everybody,” said Pete Tinoco, Boldt’s superintendent on the major remodel of Sutter General Hospital. “We had guys inside and outside at the same time, keeping an eye on the panels as they were moving, just to make sure they didn’t hang up on something and create a fall hazard.”

Because of this, communication was vital. Each panel piece required a different process of removal. It was difficult to have any kind of standard process in place.

The largest panel to be removed in one piece weighed more than 8,000 pounds. It was removed from the third floor with chain falls, a boom lift and the tower crane.

Having a very narrow bay to work in added to the challenging task.

“We didn’t have a lot of latitude for moving, or for equipment that we would have rather used,” Baudot said.

Even with all the challenges, all panels from the first, second and third floors were removed safely, on time and on schedule. Boldt and Austerman workers are now awaiting the go-ahead from the California Office of Statewide Health Planning & Development, or OSHPD, to safely remove the panels from the fourth floor of Sutter General. With that accomplished, construction crews can then finish the spanning structure by finishing the spanning structure and connecting the two hospitals. When the expansion project is completed in late 2013, this spanning structure will seamlessly connect all of Sutter Medical Center’s acute-care services under one roof.

{ 1 comment }

Even while Sacramento is experiencing near-freezing temperatures, things inside the Anderson Lucchetti Women’s and Children’s Center are really heating up … literally.

That’s because the first four floors are completely enclosed and “dried in,” keeping the cold weather out, and temporary heating will be turned on by the end of the year. This will allow construction crews to begin sheetrocking the walls and ceilings, said Pam Brink, Sutter Medical Center, Sacramento’s senior project manager on the Women’s and Children’s Center construction.

Over the past few months, the new hospital has been transformed. No longer is it just a steel structure, but most of the windows and outside walls are up, although the final exterior “skin” still needs to be installed. Inside the building, outside of public view, framing for the walls has continued as well as utility installation such as fire sprinklers, plumbing and electricity inside the walls and ceilings.

Meanwhile, the three-story spanning structure, which was slated to be completed by the end of this year, needed some changes requiring approval by the Office of Statewide Health Planning and Development, which oversees hospital construction in California. That has delayed the reopening of L Street until April 2012.

The bridge over 28th Street connecting Sutter Capitol Pavilion and the Sutter Cancer Center/Buhler Building will begin after the spanning structure is complete and L Street is reopened to traffic. To facilitate that bridge’s construction, a portion of 28th Street will be closed for a few months.

Another bridge, which will connect the South Parking Lot under the freeway to the Anderson Lucchetti Women’s and Children’s Center, will begin construction by late 2012. That bridge over 29th Street will not require a lengthy street closure, although Brink says there may be some rerouting of traffic on weekends. That bridge, which has an open-air design with a roof and screening on the sides, will be constructed off-site and installed in large sections.

{ 0 comments }

Sealing in the Winter Weather

November 16, 2011

Construction crews have been busy installing the outer walls of the Anderson Lucchetti Women’s and Children’s Center. As floors are sealed in, work can continue inside the new hospital, even in inclement weather. Click on each photo for a larger view and to see the entire width and length of each shot. After the picture [...]

Read the full article →

New Hospital Is Going Green

November 1, 2011

Autumn is the time when leaves change colors, and this fall the Anderson Lucchetti Women’s and Children’s Center is changing color, too – to a bright green. Construction crews are working at a brisk pace installing green glass-mat sheathing panels called SECUROCK in order to seal in the new hospital so work can continue on [...]

Read the full article →